CLOSE Close
MySnoPUD Sign In
Remember Me
Forgot your Password? Create an Account
"Remember me" will keep you logged in and will store your User ID on the computer you are using. Do NOT use this feature on public computers (such as those in a library, hotel, or internet cafe).

Not Enrolled?
Create a profile Make a one-time payment

Hancock Creek Hydro Project

The PUD’s Hancock Creek Hydroelectric Project is a 6 megawatt (MW) run-of-the-river hydroelectric generating facility. There is no reservoir storage associated with the project; power generation is based solely on inflow or the amount of water flowing in the creek.

Location

The project is located within the 89,500 acres of timber forest lands owned by Campbell Global Forest Management approximately seven miles north of the city of North Bend in King County, Washington. It runs between the outlet of Lake Hancock and Hancock creek’s confluence with the North Fork Snoqualmie River. The project’s permanent footprint includes 1.13 acres between the intake, penstock route, powerhouse, and access roads. The average rainfall in the area is between 60-70 inches per year, typically concentrated in the fall and winter seasons. This rainfall pattern allows for more generation during peak energy demand of the colder months.

History

The project was previously licensed by Federal Energy Regulatory Commission (FERC) in the early 1990s. Several studies were conducted, but no construction took place and the license was subsequently terminated. The PUD acquired the land in 2010 and began the scoping, permitting, and licensing processes. After environmental studies and stakeholder consultation, FERC issued a license to the PUD in June 2015. Construction began in early 2016 and was completed in February 2018.

Generation

The nameplate capacity for the project is 6 MW, with an anticipated average of 22,100 megawatt-hours to be generated annually. Run-of-the-river operation of the project means that some of the inflow is diverted from the creek, passed through turbines, and then returned to the creek downstream. No active storage reservoir is associated with the project – water not diverted through the penstock remains in the creek and flows along the natural stream course. There is no change in the quantity or quality of the diverted water as it travels down the penstock and exits the powerhouse. To protect fish and aquatic resources, a minimum instream flow is maintained in the bypass reach. During times of natural low inflow during summer, the project is not operating and all water remains in the creek.

Environment

Terrestrial

The PUD selected the project location based on the ability to avoid, minimize, and mitigate for terrestrial and other environmental impacts during construction and operation. To minimize impacts, the PUD made several design choices including: relocating the penstock route to avoid wetlands and maintain buffers, burial of 7,310 feet of penstock to eliminate barriers to animal movement, adjusting the width of the working corridor during construction, and burying transmission lines to avoid electrocution or collision risks to wildlife. Unavoidable impacts to wetlands or buffers were mitigated according to local environmental codes. Temporary impacts due to construction were mitigated by re-vegetation and will be monitored to ensure success. Noxious weeds will be managed throughout the project boundary over the life of the license. The PUD also allocated 6.59 acres of additional preservation buffer near the neighboring Calligan Creek Hydroelectric Project to mitigate impacts to both projects.

Fisheries

The project is located above Snoqualmie Falls, a natural barrier to salmon and steelhead trout. Upstream of the falls, resident trout are present throughout the watershed and in Hancock Creek. The PUD conducts annual surveys to monitor trout (principally rainbow trout) populations and their response to project operations. Minimum instream flows are maintained throughout the year to preserve fish habitat. Continuous monitoring of flow levels and water quality occurs at prescribed locations to ensure compliance. The project provides for fish passage, including a constructed fish ladder for upstream passage and includes fish screens to prevent the entrainment of fish into the project intake. If monitoring data warrants changes to project operations, the PUD will apply adaptive management methods and consult with agencies to determine appropriate modifications.

Facilities

Diversion Weir & Intake

A 46-foot wide, 6-foot tall weir was constructed for the project, which allows water not diverted through the intake to flow over it or through the fishway. The intake is equipped with self-cleaning fish screens to prevent fish and debris from entering the penstock. The intake was designed in consultation with state agencies to prevent the entrainment of fish by maintaining approach velocities of 0.4 feet per second or less.

Powerhouse & Tailrace

The powerhouse is a two-story concrete block structure housing one 6-MW Pelton turbine and associated piping and equipment. The tailrace is a 135-foot rock-lined channel with a two-foot high fish exclusion barrier that returns water to the creek after it exits the powerhouse.

Penstock

The penstock is a 1.5-mile long, 44-inch diameter pipeline that conveys the water downhill from the intake to the powerhouse. Flows can reach up to 81 cubic feet per second over a 1,100-foot vertical drop so water can build up plenty of generating power when it reaches the powerhouse. During construction, the penstock pipe sections were carefully placed in a trench and precision welded for strength. The trench was covered and seeded to provide wildlife passage over it.

Transmission lines

Buried three-phase transmission lines bring power generated by the facility approximately 2.5 miles to the electric grid.

Hancock Creek Hydro Project